DISCOM (MPPKVVCL / MPMKVVCL / MPPoKVVCL)
Net Metering
Net Metering
Net metering credits you for surplus solar energy exported to the grid. Your DISCOM replaces your single-direction meter with a bi-directional meter that records both import and export.
Typical process in MP
- DISCOM application filed alongside installation
- DISCOM load approval (usually 2–4 weeks)
- Commissioning inspection by DISCOM engineer
- Meter replacement with bi-directional unit
- First net-metered bill in the following cycle
Net-metering activation cost: ₹12,000 (DISCOM fee, separate from installation). Smart-meter inflow/outflow activation: ₹1,000.