Typical process in MP

  1. DISCOM application filed alongside installation
  2. DISCOM load approval (usually 2–4 weeks)
  3. Commissioning inspection by DISCOM engineer
  4. Meter replacement with bi-directional unit
  5. First net-metered bill in the following cycle

Net-metering activation cost: ₹12,000 (DISCOM fee, separate from installation). Smart-meter inflow/outflow activation: ₹1,000.